18
ITEMS YOU NEED:
• Battery should be 12 volt, negative ground with top posts.
ASPAS1BBA007: Minimum 350 CCA at 0° F (Group 26)
ASPAS1BBA012 & ASPAS1BBA015: Minimum 525
CCA at 0° F (Group 26)
• 40 Amp (7 kW) or 70 Amp (12 kW and 15 kW) double
pole circuit breaker (Must be compatible with your
main distribution panel.)
• Grounding rod with grounding strap
• Crushed stone or pea gravel (approximately 10-12
cubic feet)
• Black poly-film or other vegetation blocking fabric (5-
1/2' x 5')
• Silicone caulk
• Pipe sealant (suitable for gaseous fuel connections)
• Fasteners (to mount external connection box and
automatic transfer switch with built-in load center)
TOOLS REQUIRED:
Drill, drill bits, hole saw (type and length will be
determined by the materials you will be drilling and
cutting), open-end wrenches or adjustable wrenches,
socket wrenches or nut drivers, standard and Phillips
screwdrivers, level, sledge hammer, channel-lock pliers,
spade shovel, pencil and safety goggles.
Installation Preparation
Air-cooled models only.